Short answerA good wayfinding tender gives every requirement an ID and a priority (Must, Should or May), asks each bidder for a status and a piece of evidence against every line, and ends with acceptance tests run on site. The tables below are vendor-neutral: copy them, set the priorities for your building and fill in the values in square brackets.
How to use this template
Tenders name this system in different ways: “digital way finding system”, “indoor navigation system” or “interactive directory”. Whatever your document calls it, the tables below cover what it has to do, in words any capable bidder can answer.
-
You
Requirements
Copy the tables, set Must, Should or May, and fill in the values in square brackets.
-
Bidders
Compliance matrix
Each bidder gives every ID a status and a piece of evidence, not a yes.
-
You and the shortlist
Scripted demo
Shortlisted bidders run the acceptance tests on your own floor plan.
-
You and the winner
Site acceptance
The same tests, on the installed kiosks, decide payment milestones.
Before the requirements, give bidders what they need to price: buildings, floors and floor area; the drawings you hold; kiosk and screen locations; visitor languages; your hosting rule; your accessibility standard; and whether an approved emergency plan exists.
Map data and authoring
| ID | Requirement | Priority | Evidence to ask for |
|---|---|---|---|
| MAP-01 | Import the buyer’s CAD drawings in [DWG or DXF]. State every other format accepted and which conversion steps are manual. | Must | Format list with status; one floor converted from the buyer’s drawings |
| MAP-02 | Model doors, corridors, lifts, stairs, ramps and escalators as a routable network across floors and buildings. | Must | Live route across two floors |
| MAP-03 | The buyer’s staff rename places, change opening hours and hide rooms without the supplier’s help. | Must | Done by the buyer’s staff in the demo |
| MAP-04 | Role-based access, with map changes reviewed and approved before they are published. | Must | Role list; approval shown live |
| MAP-05 | Scheduled publishing, and rollback to any earlier version in one step. | Should | Rollback shown live |
| MAP-06 | Export the complete map in an open format such as IMDF or GeoJSON at any time, at no extra charge. | Must | A sample export file |
| MAP-07 | An audit log of who changed what, and when. | Should | Screenshot of the log |
Visitor wayfinding
| ID | Requirement | Priority | Evidence to ask for |
|---|---|---|---|
| WAY-01 | Search by name, category, everyday synonym and room number, tolerant of spelling mistakes, in every visitor language. | Must | Demo with the buyer’s list of test words |
| WAY-02 | Numbered step-by-step directions with distance, walking time and floor changes, naming landmarks. | Must | Directions for three test routes |
| WAY-03 | The same map and directions on kiosks, on visitors’ phones in a web browser without an app, and on the buyer’s website. | Must | All three shown on one route |
| WAY-04 | A kiosk route moves to a phone by QR code, keeping destination, language and accessibility settings. | Must | Scanned on an iPhone and an Android phone |
| WAY-05 | Opening hours per place, taken into account when a route is given. | Should | A route to a place that closes soon |
| WAY-06 | Phone positioning (a moving “blue dot”) as an option, under the POS requirements. | May | See POS-02 |
Kiosks and screens
| ID | Requirement | Priority | Evidence to ask for |
|---|---|---|---|
| KIO-01 | Runs on the hardware listed in the bid (minimum memory, operating system and browser), portrait and landscape, at Full HD and 4K. | Must | Hardware list; demo on the proposed model |
| KIO-02 | Each kiosk has a fixed position and facing direction on the map, so routes start where the visitor stands. | Must | Kiosk set-up shown in the CMS |
| KIO-03 | The session resets after [60] seconds idle, clearing search, route, language and accessibility settings. | Must | Acceptance test T6 |
| KIO-04 | Keeps searching and routing from a stored map when the network fails, and recovers without a site visit. | Must | Acceptance test T5 |
| KIO-05 | Remote monitoring: online status, offline alerts, remote reload and screenshot. | Must | Fleet screen shown live |
| KIO-06 | Map, directory and notices available to the buyer’s existing signage players by URL or feed (for example RSS, JSON Feed or iCalendar). List the player models tested. | Should | Player list with test status |
Accessibility
| ID | Requirement | Priority | Evidence to ask for |
|---|---|---|---|
| ACC-01 | Step-free routes never use stairs or escalators. Where no step-free route exists, the system says so. | Must | Acceptance test T2 |
| ACC-02 | Route options for at least wheelchair users and visitors avoiding stairs. | Must | Both shown live |
| ACC-03 | A kiosk mode that brings every control within reach of a seated user, following [the accessibility standard named by the buyer]. | Must | Shown on the proposed kiosk |
| ACC-04 | Large-text and high-contrast modes. State the contrast ratio achieved. | Must | Measured ratio; demo |
| ACC-05 | Spoken directions in each visitor language, on the proposed hardware. | Should | Played on the kiosk in each language |
| ACC-06 | A written accessibility statement naming the WCAG version and level the visitor interface is designed to, with any independent audit report and its date. | Must | The statement and any report |
Languages
| ID | Requirement | Priority | Evidence to ask for |
|---|---|---|---|
| LAN-01 | All visitor-facing text in [English, Arabic, Hindi], with right-to-left layout wherever a language needs it. | Must | Kiosk shown in each language |
| LAN-02 | An on-screen keyboard for each script listed in LAN-01. | Must | Each keyboard shown |
| LAN-03 | Search matches common spelling variants in each language, such as Arabic letter forms. | Must | Demo with the buyer’s test words |
| LAN-04 | The buyer approves each translated string before it is published. | Should | Approval workflow shown |
| LAN-05 | The bid lists every LAN-01 language for which a font, keyboard or interface translation is not included. | Must | The list, or a statement that none is missing |
Live operations and emergencies
| ID | Requirement | Priority | Evidence to ask for |
|---|---|---|---|
| OPS-01 | Closures and notices reach all or chosen screens within [60] seconds without republishing the map, and active routes avoid them. | Must | Acceptance test T3 |
| OPS-02 | An emergency message on every screen in every visitor language, started and ended only by authorised staff. | Must | Acceptance test T7 |
| OPS-03 | A route to the nearest available exit, using exit data approved by the buyer. It supplements, and does not replace, alarms, signs and staff. | Should | Demo on the buyer’s floor plan |
| OPS-04 | Notifications to other systems, such as signed webhooks, when an emergency starts or a kiosk goes offline. | Should | Event list; sample payload |
Phone positioning (optional)
| ID | Requirement | Priority | Evidence to ask for |
|---|---|---|---|
| POS-01 | Phone positioning delivered first as a pilot in [one zone], before any wider roll-out. | May | Pilot plan |
| POS-02 | Accuracy measured on the buyer’s site: test points, phone models, error at the [95th] percentile and share of fixes on the correct floor. | Must | Measurement report from the pilot |
| POS-03 | Supported phones and operating systems, and whether visitors need to install an app. | Must | Written list |
| POS-04 | Any beacons: model, spacing, battery life, survey method and maintenance plan. | Should | Installation and maintenance plan |
Hosting, security and privacy
| ID | Requirement | Priority | Evidence to ask for |
|---|---|---|---|
| SEC-01 | Every hosting option offered: supplier cloud in a region named in the contract, dedicated cloud, or a server on the buyer’s network. | Must | Deployment diagrams |
| SEC-02 | If on-premises: installation on the buyer’s server, with backup, restore and upgrade procedures, and a list of every outbound connection. | Must | Operations manual; connection list |
| SEC-03 | Operation with no internet connection, with offline updates. | Should | Shown on a disconnected server |
| SEC-04 | No personal data collected from visitors at kiosks. Statistics are anonymous, with the retention period stated. | Must | Data inventory; acceptance test T10 |
| SEC-05 | Staff sign-in with roles, and single sign-on through [SAML 2.0 or OpenID Connect]. | Should | Configuration guide |
| SEC-06 | Security documents: architecture or threat model, a completed security questionnaire, and the report or scope of independent penetration testing. | Must | The documents, under NDA if needed |
| SEC-07 | The certifications or attestations held (for example ISO/IEC 27001), with scope and expiry, or a plain statement that none are held. | Must | Certificates, or the statement |
| SEC-08 | A mapping of the system’s controls against [the applicable data-protection law], for the buyer’s legal review. | Should | The mapping document |
Statistics, integration and support
| ID | Requirement | Priority | Evidence to ask for |
|---|---|---|---|
| DAT-01 | Statistics on searches, destinations, searches with no result and kiosk use, exportable as CSV with [the columns the buyer specifies]. | Must | Sample export |
| DAT-02 | A documented API, with access keys that can be limited to one venue. | Should | API reference |
| SUP-01 | A project plan with phases, listing what the buyer must provide and when. | Must | The plan |
| SUP-02 | Operator and administrator manuals, and training for the buyer’s staff with a sign-off. | Must | Manual contents; training outline |
| SUP-03 | Support hours, channels and response times in the contract, and how kiosk faults are fixed on site. | Must | Draft support schedule |
| SUP-04 | Any availability commitment, with how it is measured and reported. | Must | Draft contract clause, or a statement that none is offered |
| SUP-05 | References for comparable installations, or a plain statement that none exist yet. | Must | Names and contacts, or the statement |
Status words for the compliance matrix
Ask for the matrix as a spreadsheet with one row per ID: status, evidence reference and any limit.
-
Evidenced
- Means
- Shipped and working today, in the version you would receive.
- Evidence
- A live demo, a test record, a document or a reference you can call.
- Scoring
- Full marks, once you have seen the proof.
-
Partial
- Means
- Works with a stated limit, or needs work by you or a third party.
- Evidence
- The same as Evidenced, plus the limit in writing.
- Scoring
- Part marks. Read the limit carefully.
-
Roadmap
- Means
- Planned, not available today.
- Evidence
- A delivery date the bidder will put in the contract.
- Scoring
- Treat as not met unless the date is contractual.
-
Not offered
- Means
- The bidder does not provide this.
- Evidence
- None. An honest “no” beats a vague yes.
- Scoring
- Not met. On a Must, it rules the bid out.
Reading a matrix: an example
This extract is invented. It shows why the evidence matters more than the status a bidder picks.
Compliance matrix, extract
| ID | Bidder’s status | Bidder’s evidence | Evaluator’s note | Result |
|---|---|---|---|---|
| KIO-04 | Evidenced | Video of a kiosk routing with Wi-Fi switched off | A good start. Repeat it live in the demo with the network cable pulled. | Pending demo |
| ACC-01 | Evidenced | Brochure, page 6 | A brochure is not evidence. Partial until a step-free route is shown with the lift closed. | Partial |
| LAN-02 | Partial | Arabic keyboard today; Urdu keyboard “planned for Q3” | The Urdu half is Roadmap. Ask for the date in the contract. | Partial |
| POS-02 | Evidenced | “Accuracy 1 m” | No site, no test points, no phones named. The method POS-02 asks for is missing. | Not met |
| SEC-07 | Evidenced | Statement that no certifications are held; security questionnaire attached | Meets SEC-07, which asks for a plain answer. Score the documents under SEC-06. | Met |
| SUP-05 | Evidenced | Two reference sites named, with contacts | Call both, without the bidder on the line. | Pending calls |
Acceptance tests
Run these in the scripted demo on your floor plan, and again on the installed system before final payment.
| Test | Covers | Method | Pass when |
|---|---|---|---|
| T1 Search | WAY-01, LAN-03 | Type [20] words from the help-desk list, including misspellings, on two kiosks | At least [19] lead to the right place |
| T2 Step-free | ACC-01 | Route between two floors with step-free on, then close the lift it used | The route moves to another lift, or the screen says no step-free route exists |
| T3 Closure | OPS-01 | Close a restroom in the CMS | Every screen shows it and routes avoid it within [60] seconds |
| T4 Phone hand-off | WAY-04 | Scan the kiosk QR code on an iPhone and an Android phone, on mobile data | Same route, language and step-free setting on both |
| T5 Offline | KIO-04 | Disconnect a kiosk’s network for [30] minutes | Search and routing keep working; it shows as offline, then recovers |
| T6 Reset | KIO-03 | Walk away from a kiosk mid-route | Everything clears after the idle time |
| T7 Emergency | OPS-02 | Start a test emergency message, then end it | Every screen, every language; only authorised staff can end it |
| T8 Export | MAP-06 | Export the map | The file opens in a third-party GIS tool |
| T9 Rollback | MAP-05 | Publish a change, then roll back | The earlier version is live on every screen |
| T10 Privacy | SEC-04 | Inspect a statistics export | No personal data; search text handled as the bid stated |
For a fuller set of on-site checks on each kiosk, use our kiosk acceptance testing checklist.
Clauses to leave out
- An accuracy figure with no method. Use POS-02, or bidders will quote their best laboratory number.
- One vendor’s feature names. They narrow the field and invite challenge.
- “Unlimited languages”. List yours, so bidders say what is missing.
- A yes or no box for accessibility. Use ACC-06, and test ACC-01 on site.
- One certificate as a pass-or-fail gate, when the SEC-06 documents tell you more.
If you are still choosing a kind of system, read how to choose indoor wayfinding software. For public buildings that must keep data on site, see wayfinding for government buildings.
Related questions
Can we copy this specification into our own tender?
Yes, it is written to be copied and edited. Delete what you do not need, adjust the priorities and keep the IDs, so every bidder answers line by line and the same IDs carry through to the demo and the acceptance tests.
Should a tender ask for a positioning accuracy figure?
Only with the method attached. Ask bidders to report accuracy measured on your site, with the number of test points, the phones used, the error at a stated percentile and how often the floor was right. A figure without a method cannot be compared between bidders.
How should we score the bids?
Treat each Must as pass or fail on its evidence, and score Should items on a small scale, such as 0 to 2. Score price separately. A bidder who marks something Not offered is easier to evaluate than one who says yes to everything.
Should we require security certifications?
Ask which certifications or attestations the bidder holds, with scope and expiry, and ask for the documents behind its security practice. Making one certificate a pass-or-fail gate can rule out capable bidders, so consider accepting equivalent evidence and scoring it.
Who should run the acceptance tests?
Your own staff, on the installed kiosks and on their own phones, with the supplier present. Write the pass criteria into the contract before installation so nobody argues about them afterwards.